Milman Road Medical

Milmanroad6

Project Details

Client:   NHS England/Milman Road Medical Centre
Architect:   Niblett Arctitects
Value: £ 1.5m
Duration: 50 Weeks
Contract : JCT Intermediate Building Contract

Project Description

The construction of two single storey extensions to the existing Milman Road
Health Centre, creation of an internal space at 2nd floor level, fit-out of all new rooms / areas together with the complete refurbishment of the existing building including over 60 rooms undergoing a change of use.

Stoke Mandeville Hospital

fnh-extension-3100

Project Details

Client:   Stoke Mandeville Hospital – Florence Nightingale Hospice
Contract Administrator:   Sweett Group
Value: £ 180k
Duration:   14 Weeks
Contract : JCT Minor Works with Contractors Design

Project Description

To design and build an extension to the day room, ward and reception area with associated refurbishment of The Florence Nightingale Hospice.

Operational issues: The Hospice wanted to limit the impact of the construction work to the normal day to day service. RBS produced a programme that details when the works will start and finish with details of each element of work, for example removal of roof/windows/heat and power, so that the Hospice can plan service continuity without undue disruption.

Yeovil Hospital

yeovil7

Project Description

The Department of Health has given a public commitment to eliminating mixed-sex accommodation, bathroom and toilet facilities for hospital inpatients. As a result, Resource were approached by Yeovil Hospital, who provided a trusted solution – We supplied and installed floor-to-ceiling partitioning specifically designed for the healthcare industry to create 13 individual bays. Within each run, two partitions were installed, allowing the installation of a double glazed window into which we installed integral privacy blinds.

Cleaning is a major issue for healthcare providers; after preparing the floor, vinyl coved upstands were installed, eliminating gaps between the floor and partitioning. The design of the central steel stud allows the void depth to be increased up to 600mm, enabling services such as gas, electrics and air to be carried and concealed. This, coupled with the sealed window units, allows easy regular cleaning. Steam cleaning can also be used on the floors and walls to ensure continued high levels of hygiene. As working hours were restricted due to the requirements of the busy ward, Resource carried out the improvements over three consecutive weekends, starting at 19.00 on Fridays.